As of mid-January Concrete Footings were poured and passed inspection the week between Christmas and New Year’s Day. Foundation walls & insulation have been laid and have also passed inspection so trenches can be back-filled. Our next step in the construction process is for under-slab utilities to be dug and installed. Soon after that will come the concrete slab, and then framing can begin.